The River Rouge flagship anchors GPE's Michigan cluster, a utility-grade, hydrogen-ready hybrid power campus designed for grid independence and multi-fuel resilience, with a parallel 300+ MW corridor opportunity in North Carolina.
The Phase 1 working configuration (approximately 250-300 MW at full initial buildout) blends dispatchable thermal generation, multi-fuel capability, storage, and renewables, fully integrated with SCADA, EMS, and NERC-CIP-compliant cybersecurity.
| Generation Block | Capacity | Role |
|---|---|---|
| Natural gas steam turbines | 100 MW | Baseload backbone |
| Hydrogen fuel cells | 100 MW | Clean firm capacity, H₂ pathway |
| Jenbacher multi-fuel engines (H₂-capable) | 80 MW | Fast-start dispatchable capacity |
| Battery energy storage (BESS) | 10 MW | Load balancing & frequency response |
| Solar PV | 10 MW | Daytime energy contribution |
Industrial zoning within a legacy industrial corridor; proximity to water, transmission, and logistics with railroad access; Detroit Metro industrial land, political alignment, and grid proximity; MISO alignment and compliance; IRA-aligned tax credit eligibility.
Site identified and screening initiated; preliminary land-use and zoning alignment; utility and grid logic validated; city-level relationships established; EGLE air permitting initiated; FERC interconnection filing in progress; hardware allocation secured; early EPC and vendor engagement underway.
Lead developer: GeoPrime Energy. Co-engineering: Jenbacher, Black & Veatch, Clarke Energy. Technology co-development: Pratt Miller. Environmental & permitting: ERM.
City of Detroit, Wayne County, State of Michigan, MISO. Land use & zoning, environmental & water adjacency, power generation & substation approvals, grid interconnection.
300+ MW corridor opportunity in active diligence, the largest single component of the 600+ MW pipeline.
Leverages the identical engineering, permitting, and EPC frameworks developed for River Rouge, compressing development timelines and cost.
Secure strategic site control, followed by feasibility completion and anchor offtake engagement.
A 1-5 MW pilot serving as the first-to-close asset and immediate proof-of-concept for the GPE execution model: LOI executed and site control secured, PPA under negotiation with a local anchor tenant, and a 12-18 month path to commercial operation. The pilot also provides a strategic positioning site for HG-250 prototype demonstration.